2006-2007 Rehabilitation of Kechut Dam

The project anticipated strengthening the dumb, to build a new spillway and set the alert system.

The following scope of work was implemented:
1. Earthworks
19482 m³
2. Asphalt carpet
41233 m²
3. Concrete and reinforced concrete
1358 m³
4. Installation of reinforcement
71.8 t
5. Shotcrete
2652 m²
6. Precast reinforced concrete
38 m³
7. Insulation of pipelines
859 m
8. Cement injection
8766.5 m²
9. External insulation
3698 m²