2007-03-05

2007 Strengthening of the Left Bank of the River of Araks

The Client:
State Procurement Agency

Within the framework of the project rehabilitation of 22 bordering constructions of the River of Araks in Armavir Marz was executed.

The following scope of work was implemented:
1. Earthworks
5210 m³
2. Rough walling in gabion
13285 m³