2008-02-16

2008-2010 Yerevan Combined Cycle Power Plant

Source of financing:
Japan International Cooperation Agency
The Client:
”Yerevan TPP” CJSC of the Ministry of Energy and Natural Resources of the Republic of Armenia
Consultant:
TEPSCO LTD, Japan
EPC Contractor:
Consortium of Mitsui & Co LTD and GS Engineering & Construction company, Japan and South Korea

Installed (electric and thermal) capacity of the Power Unit: 271,7 MW
Installed electric capacity of the Power Unit: 242 MW

By putting the new Power unit into operation, the reliability of the Power System was increased, the regimes of supply on the loading curve was improved, the rates of flows inside the system were optimized, thus decreasing electric losses in electric networks.

The following main scope of work was implemented:
1. The earthworks
203318.3 m³
2. Concrete and reinforced concrete
14150.69 m³
3. Installation of reinforcement
1400 t
4. Steel structures
50 t
5. Laying of pipelines
2984.75 m
6. Asphalt carpet
11500 m²