After reconstruction of 260 meters long section of drainage tunnel No. 2, “ArmHydroEnergyProject Institute” CJSC developed the design for reconstruction of 667 meters long section of drainage tunnel No. 2.
Previously collapsed tunnel section was recovered. Driving, concrete laying, drainage holes drilling and injection volumes were done.