2016-03-31

2016-2018 Dilijan Drainage Tunnel Reconstruction

The Client:
“Metsn Erik” Ltd.

The project was developed by “ArmHydroEnergyProject Institute” CJSC. It was implemented as reconstruction of 550 m long section of the drainage tunnel N2, which prevented the landslide danger at Tala district of Dilijan town. Previously collapsed parts of old tunnel were recovered. Driving, concrete laying, drainage holes drilling and injection volumes were done.